Sinking billions - undergunned and over priced - part 1
July 6, 2023
Missing records, billions in over-runs, conflicts of interest, and flawed ships. How the Australian Defence Departments new frigates project is a boondoggle for a British weapons-maker.
In a two-part investigation, _Declassified Australia_examines the flawed contracting process that led to a $46 billion navalship-building dealthat has been found to be suffering what an investigative audit described as corruption vulnerabilities.
The company at the centre of the scandal, the UKs arms giant, BAE Systems, is revealed to have lied to Australias Defence Department about the planned ships design.
Crucial departmental records of key decision-making meetings have gone missing, and no overall assessment of whether the selected BAE design was value for money was ever made.
The Australian National Audit Office (ANAO)reportedin May its findings on the multi-billion dollar contract Australia signed in December 2018 with BAE Systems to build nine Hunter-class frigates.
ANAO found that BAE had over-stated bureaucrat language for lied the level of development of the frigates design, which meant cost inflation and schedule slippage were severely under-estimated.
BAE exaggerated the maturity of its design to get around a key government objective requiring the ship to be based on an existing military-off-the-shelf design with a minimum level of change.
Defence selected the BAE Systems frigate even though the two other ships on its shortlist were considered the two most viable designs.
Business as usual
Conflicts of interest, secret consulting deals, and revolving door appointments, all undermine democracy, yet this is business as usual at the Defence Department, the nations biggest procurement agency.
Former senior BAE executives have been placed at the heart of Australias naval procurement. They have helped write government shipbuilding policy, have overseen the Navys largest tenders, and have even been hired by the government to negotiate on its behalf with their former employer on a deal now found to be riddled with probity concerns.
Granting preferential access to certain arms industry insiders escalated under previous Liberal-National Coalition governments and since 2022 has continued under the Albanese Labor government. So this is also a story aboutstate capture when a corporation has the power to bend governments to its will.
When combined with departmental corruption or incompetence, or both, the result is Defence procurement projects that are billions of dollars over budget and running years late. As a result the Navy is facing massive capability gaps.
Whose interests were served?
Defending the Departments decision not to assess the contracts value for money, Defence told the audit office, The Government determined there to be value for money in establishing a sovereign, sustainable, cost-competitive continuous shipbuilding program in Australia.
But the Australian Audit Office said Defence had conflated an objective of industry policy with the mandatory requirement of achieving value for money in procurement. The auditors said the Commonwealth procurement rules oblige departmental officials to assess value for money.
Interestingly, Defence did undertake value for money assessments on two other shipbuilding tenders it was running at the same time, both also under the nations Shipbuilding Plan the Offshore Patrol Vessels and the Cape-class Patrol Boats.
Another mandatory requirement, a whole-of-life cost estimate for the frigates, was also not provided to government.
Within 24 hours of the ANAO reports release, the Parliamentary Joint Committee of Public Accounts and Audit had launched an urgentinquiry.
Auditor-General Grant Hehir criticised the programs probity adviser, the Australian Government Solicitor (AGS), and the Finance Department, which oversees the procurement rules.At the committees firstpublic hearing, on 19 May,Hehir said that while the AGS had mentioned value for money to Defence it drifted away pretty quickly and didnt pursue the issue:
Youd expect people with responsibility for frameworks and issues like adhering to the law, which the procurement rules are, would hang on pretty tightly.
Responding to criticism of its inability to produce key documents, the Defence Department countered that these numbered less than 10, and that more than 730,000 other documents were available. This remark was signed off by the two most senior Defence leaders in the country Defence Secretary Greg Moriarty and the Chief of the Defence Force General Angus Campbell.
The Auditor-General didnt let their remark pass unnoticed at the parliamentary hearing. Our concern is not just that all records should be kept but, particularly, important records should be kept, he said In this case, [they] were significant records.
The audit report noted Defence was a serial offender of deficient record-keeping. Perhaps its most pointed comment, however, was contained in a footnote quote from the Commissioner for Law Enforcement Integrity:
Lack of record keeping can create corruption vulnerabilities within an Agency.
Senior audit office official Dr Tom Ioannou added: We pursued this at length with Defence [giving] them every opportunity to provide the documented rationale [for shortlisting BAE]. The Defence Secretary was the decision-maker on the shortlisting of BAE.
Ioannou also said that minutes were unavailable of the Defence Committee meeting at which the decision to recommend BAEs frigate was likely discussed. This is an apex Defence enterprise level committee with well-established and elaborate secretariat arrangementsdesigned to capture exactly this sort of decision-making, he said. This is the highest level committee in Defence and includes the Defence Secretary and the Chief of the Defence Force.
Suspicions exist of potential corruption in the multi-billion dollar contract.Possible nefarious conduct was suggested more than once by Committee chair Labor MP Julian Hill, while deputy chair, Liberal senator and former Defence minister Linda Reynolds, referred to BAE Systems as a very wily contractor.
Faced with a multitude of questions they could not answer, officials said the Department was conducting an internal investigation and would report back. The next hearing is likely to be in late July or August.
Over-stated design maturity
One of the governments five project objectives was that the frigate be based on a military-off-the-shelf design with a minimum level of change, but the shortlisting of BAEs frigate was criticised for not meeting this criteria because it was still in the design phase and not yet in the water, unlike the other two shortlisted ships.
To counter this criticism, BAE Systemsstatedits design would be de-risked because the Australian program was running five years behind the UK program, meaning the Royal Navy would resolve design issues ahead of the Australian program.
Despite those claims, the audit report found that the immaturity of the ships design was mostly to blame for mounting costs and schedule delays.
Australian taxpayers are paying BAE Systems more than $6 billion for the design and productionisation of the frigates.
Expressing consternation that BAE made the shortlist, Australias Chief of Navy from 1999-2002, former vice admiral Dr David Shackleton, said, Given the degree of redesign needed to progress to this point, its reasonable to question how [it] was placed on the list of contenders in the first place.
As for the high design costs, Dr Shackleton said some explanation was needed. In his 202248-page reporthe stated:
How Australia found itself paying $6.26 billion to modify an existing design that was ostensibly mature enough for the UK to start construction, and one that was proclaimed to be readily amenable to change, needs some explanation.
Comparing costings across procurements is extremely difficult due to individualised modifications to suit a countrys requirements and the secrecy cloaking contractual arrangements. Yet the apparent magnitude of the difference between the Australian, Canadian and US procurements is startling.
The Canadian Navy is acquiring and modifying the same BAE frigate as Australia. Canadas initial design modification contract was forCA$185million($205 million). Canadanotedthis amount would increase as the design evolved.
Dr Shackleton told_Declassified Australia_that at face value the Canadian figure appears to be high, particularly when an advantage of the ship was purportedly its modern digital design, being ostensibly less difficult to modify than traditional methods normally involve.
This view is supported by a contract the US Navy signed in 2018 with Italian shipbuilder Fincantieri to modify its frigate to suit US needs, aUS$15 million($21 million). A US Congressional Budget Officereportsaid the US frigates design costs could rise if design changes were made during construction.
The Defence Department is well known for excessive secrecy. It has not been transparent about the amount Australia is paying for the design modification.
Defencehas saidthe $6 billion price tag for the Hunter-class frigate programs design and productionisation covers three elements: design modifications, prototyping of ship blocks at the new Osborne shipyard, and ordering long-lead items for the first three ships.
_Declassified Australia_asked Defence for a breakdown of the $6 billion and for more detail regarding the long-lead items. The Department did not respond to our request.
BAE frigate unsuited for needs
Former Navy chief David Shackleton has called for the program to be scrapped and the funds redirected into acquiring ships that are more suitable. Hisreportfound that:
A misguided emphasis on optimisation for Anti Submarine Warfare operations has resulted in Australia choosing a ship unsuited for its needs.
Dr Marcus Hellyer, a former senior analyst at the Australian Strategic Policy Institute, also listedsimilar concernsand alternative proposals. Hellyer noted:
[BAEs frigate] is under-gunned for the threat environment of the 2030s: its missile capacity is the most glaring shortfall its 32 missile cells mean its taking a knife to a gunfight.
The audit report said Defence was not even able to provide an estimate of the final cost of the frigates. It could say only that the cost was likely to be significantly higher than the $44.3 billion previously advised to government. This was already $10 billion more than the original $35 billion cost.
The cost blowouts are now so significant that the frigate program is unaffordable without cost cutting elsewhere or reducing the number of ships, according to Defence officials quoted in the audit report.
Defence investigated BAE over fraud claims
The auditors report is not the first time questions have been raised about the nature of the relationship between the Australian Defence Department and BAE Systems.
In 2018 Defence commenced asecret investigationinto BAE Systems overallegationsthat Navy contracts have been inflated by tens of millions of dollars by being stuffed with unsubstantiated expenses.
The inflation of BAE invoices by tens of millions of dollars allegedly occurred during its sustainment work on an earlier class of Australian frigates, the now-decommissioned Adelaide-class, under a contract awarded to BAE in 2008 without a competitive tender process.
Concerns about BAEs invoicing had reportedly been first raised within Defence in 2014. However, Defence began its secret investigation four years later, in response to a whistleblower, but only after BAE had been awarded the Hunter-class frigate contract.
BAE was not alone in eliciting concerns over corruption vulnerabilities. Defence also investigated Thales Australia, its second largest weapons contractor, at the same time for invoicing irregularities on the same Frigates.
Aninternal Defence auditfound BAEs Adelaide frigates contract had been reportedly riddled with cost overruns, with the British company consistently invoicing questionable charges.
So serious were the fraud allegations against BAE Systems they were escalated to Defences Assistant Secretary of Fraud Control, who referred several matters to the Independent Assurance Business Analysis and Reform Branch of the Defence Department.
When I asked Defence about the results of its secret investigations into BAE Systems, Defence Media responded that its investigation had found no evidence of inappropriate excess charges.
BAEs sordid record
BAE Systems is Australias largest Defence contractor and the worlds sixth largest arms corporation.It has a sordid record of corruption globally as well as selling weapons to war crime abusers.
During the 1990s and 2000s, in a deliberate choice that came from the top, BAE Systems maintained an offshore shell company in the Cayman Islands called Red Diamond Trading that was used to channel hundreds of millions in bribes to key decision makers in a succession of arms deals.
The largest of these arms deals were the 43 billion ($82 billion) deals with Saudi Arabia known as_Al Yamamah_. Aninvestigationby the UKs Serious Fraud Office uncovered billions in commission payments, or bribes, paid by BAE Systems to members of the Saudi royal family and others, including for visits to the UK and foreign travel.The investigation was cancelled in 2006 by PM Tony Blair under pressure from BAE and the Saudis.
The Saudi War in Yemen has seendevastation and thousands killed, and over 4 million Yemenis fleeing their homes. But it has been good for business for BAE Systems.
BAEs former chairman, Sir Roger Carr, wassecretly recordedin 2019 making comments to shareholders on the war in Yemen. Civilians_are_killed in war. The solution is to stop wars at the earliest opportunity. And our belief is that if you supply first class equipment, you are the encouragement, particularly when used in defence, for people to stop fighting.
BAE has certainly shown a unique way of ensuring business and ethics can co-exist.
Next time, in Part Two of Sinking Billions:
The deeply intertwined connections between warship builder BAE Systems and the Australian Department of Defence.
First published by Declassified Australia July 3, 2023
Michelle Fahy,
Michelle is an independent researcher specialising in investigating links between the weapons industry and Australian government. Her work has appeared in Progressive International, Arena, Declassified Australia, Michael West Media and elsewhere. Member of MEAA.